Associating a quality gate with projects

The default quality gate is associated with all projects in the organization that are not explicitly associated with a quality gate.

The default quality gate is associated with all projects in the organization that are not explicitly associated with a quality gate. You can explicitly associate a project with a quality gate:

Last setting overrides principle without a hierarchy

The last setting overrides principle applies without a hierarchy: the most recently configured setting will take precedence over all previous settings. For example:

  1. From the Quality Gates page, you first associate quality gate 1 with project 1.

  2. Still from the Quality Gates page, you associate quality gate 2 with project 1. Project 1 is now associated with quality gate 2.

  3. From project 1 settings, you associate project 1 with quality gate 3. Project 1 is now associated with quality gate 3. The setting is updated in the Quality Gates page.

  4. From the Quality Gates page, you associate quality gate 1 with project 1. Project 1 is now associated with quality gate 1. The setting is updated in project 1 settings.

circle-exclamation

Associating projects with a quality gate

  1. Retrieve your organization. See Retrieving your organizations for details.

  2. Go to Quality Gates.

  3. In the left panel, select the quality gate you want to manage.

  4. In the Projects section on the right, select the With (to view only the associated projects), Without (to view only the disassociated projects) or All tab.

  5. Select or unselect the projects you want to associate with or disassociate from the quality gate.

Associating projects with a quality gate

Last updated

Was this helpful?