Start Free
Latest | Instance administration | System functions setup | PDF reports

Setting up PDF reports

On this page

Project and application PDF reports

As a system administrator, you can change the PDF report subscription frequency of all projects and applications or for each project or application individually:

  • Global-level:To change the frequency setting globally, navigate to Administration > General Settings > Governance. Under Project and Application PDF Reports, select an option from the PDF Reports Frequency drop-down menu.
  • Project-level: To change the frequency setting for a specific project, navigate to the project's home page then Project Settings > General Settings > Governance. Under Project and Application PDF Reports, select an option from the PDF Reports Frequency drop-down menu.
  • Application-level: To change the frequency setting for a specific application, navigate to the application's home page then Application Settings > Application Report Settings, and select an option from the Application Reports Frequency drop-down menu.

You have the following options for subscription frequency:

  • Daily 
  • Weekly 
  • Monthly (default)

Portfolio PDF reports

As a system administrator, you can configure the subscription frequency for all portfolios globally or for each portfolio individually.

  • Global-level: To change the frequency setting at a global level, navigate to Administration > General Settings > Governance, and in the Portfolio PDF reports section, select a frequency from the drop-down menu.
  • Portfolio-level: To change the frequency setting for a specific portfolio, navigate to the portfolio's home page then Portfolio Settings > Executive Report and select an option under Frequency.

You have the following options for subscription frequency:

  • Daily: report is sent during the first portfolio calculation of the day (if any)
  • Weekly: report is sent during the first portfolio calculation of the week (if any) from Monday
  • Monthly (default): report is sent during the first portfolio calculation of the month (if any), starting from the first day of the current month

Sending portfolio PDF reports to non-SonarQube users

Users with administrative rights on a portfolio can send the portfolio PDF report to non-SonarQube users by adding their email in the Other Recipients field at Portfolio Settings > Executive Report.


Was this page helpful?

© 2008-2024 SonarSource SA. All rights reserved. SONAR, SONARSOURCE, SONARLINT, SONARQUBE, SONARCLOUD, and CLEAN AS YOU CODE are trademarks of SonarSource SA.

Creative Commons License